top of page

Marksbury Plain Solar Farm – Primary & Secondary Substations

A major renewable energy development near Bath for European Energy

PHOTO-2024-08-13-13-53-58-10-980x735.jpg

The Challenge

As a multi-phase renewable development, the project required:

​

  • A coordinated substation strategy across primary and secondary assets

  • High-quality enclosures delivered ready for rapid connection and testing

  • Minimal programme risk to maintain momentum across construction phases

  • Infrastructure designed for long-term operational performance

​

All works needed to align with European Energy’s sustainability goals and strict grid compliance requirements.

Outcome

All substations were successfully delivered and installed in line with programme requirements, supporting a solar farm that will:

​​

  • Generate up to 15MW of renewable electricity

  • Power approximately 4,700 homes with clean, home-grown energy

  • Operate for up to 40 years

  • Prevent an estimated 304,000 tonnes of CO₂ emissions, equivalent to removing 176,000 cars from UK roads

​

The project also contributes to local environmental enhancement through biodiversity-focused land use proposals.

Check out the rest of our projects

News

Why Choose B&S Group

We work as a trusted engineering partner, delivering power infrastructure that supports the UK’s transition to a resilient, low-carbon energy future.

Over 30 years of engineering expertise

In-house fabrication and integrated delivery

Proven experience in regulated and safety-critical environments

A focus on quality, compliance, and long-term performance

Project Overview

B&S Group was appointed to deliver Phase 1 and Phase 2 substation infrastructure for the Marksbury Plain Solar Farm, a major renewable energy development near Bath for European Energy.

The project forms part of the UK’s growing solar generation capacity, delivering long-term clean energy while enhancing local biodiversity and environmental outcomes.

B&S Group Solution

B&S Group provided a comprehensive scope of works, including:

​

  • Design and installation of 1 x Primary Switchgear Enclosure

  • Design and installation of 4 x Secondary Transformer Substations

  • In-house fabrication to ensure quality, consistency, and programme certainty

  • Delivery of all five enclosures fully completed and ready for connection

​

By managing the entire process internally, B&S Group ensured tight control over quality, timelines, and risk throughout both project phases.

Client:
European Energy

Sector:

Energy Generation
Solar PV

Capability:

Primary & Secondary Substations
Turnkey Renewable Infrastructure